School Washroom Refurbishment at The Hawthorns School, Chelmsford

Refurbishment and reconfiguration of a school washroom and accessible WC in Chelmsford, with additional cubicles, relocated handwashing facilities, a new access point and durable commercial finishes.

Location
Chelmsford, Essex
Project Cost
£25,000 + VAT
Duration
5 Weeks

The Client's Vision

The Brief

What the client wanted

The existing washroom and accessible WC needed more capacity and a layout that worked better for the school. The brief called for additional cubicles, handwashing facilities in a more practical position and a new access point, with the existing doorway removed from the revised arrangement.

What we delivered

Belvia stripped out the existing fittings and finishes, rebuilt the internal layout and formed the new doorway. New plumbing and electrical services were installed before the partitions were boarded and plastered. The completed space includes new cubicles, a low-level vanity, a refitted accessible WC, full decoration and commercial-grade vinyl flooring.

Project Highlights

  • Additional cubicles created within the reworked layout

  • Handwashing facilities relocated to improve the use of the space

  • New access point formed and the redundant doorway infilled

  • Plumbing and electrical services renewed for the revised arrangement

  • Accessible WC, commercial vinyl floor and complete internal decoration

What We Delivered

A complete washroom reconfiguration, from strip-out and new partitions through to services, finishes and final fit-out.

Scope of Works
  • Existing sanitaryware, partitions and finishes removed
  • Existing services exposed for the revised layout
  • New partition walls formed for the additional cubicles
  • New doorway created and the redundant opening infilled
  • New plumbing installed for the rearranged facilities
  • Electrical services adapted to suit the new layout
  • Boiler and booster-pump installation completed within the plant area
  • New partitions boarded around the concealed services
  • Walls plastered ready for decoration
  • New cubicle doors and fittings installed
  • Low-level vanity and taps fitted in the relocated handwashing area
  • Accessible WC suite installed within the revised layout
  • Grab rails, low-level basin and associated fittings completed
  • Commercial-grade vinyl flooring laid throughout
  • Walls, linings and joinery fully decorated
  • Final second-fix and finishing work completed

Specifications & Materials

Key Details

Cubicles

Oak-effect doors and partitions with teal-painted linings and pictogram signage.

Handwashing

Low-level vanity with two basins and wall-mounted taps.

Accessible WC

WC, low-level basin, grab rails and associated fittings.

Flooring

Light grey commercial-grade vinyl flooring.

Services

New plumbing and electrical services for the revised layout.

Decoration

Full internal decoration with teal joinery accents.

Outcome

The Result

The completed washroom makes better use of the available space, with extra cubicles, a clearly defined handwashing area and a fully refitted accessible WC. The teal joinery, oak-effect doors and light flooring give the rooms a consistent finish that is practical for daily school use.

The project also shows the work that sits behind the visible finish. New partitions, access changes, plumbing, electrics and plant-room work were coordinated as one refurbishment rather than treated as separate repairs.

For similar education projects, see Belvia’s school refurbishment services and its wider work as builders in Chelmsford.

Start Your Project

Planning a School Washroom Refurbishment?

We can survey the space, plan the work around the school's access requirements and coordinate the full refurbishment through to handover.